The DC Department of Buildings issued 3,801 permits between October 1 and October 29, 2026. That's 3% fewer than in the same stretch of September and 6% fewer than October 2025. Underneath that small dip, the mix changed: additions rose, solar fell sharply, and full construction permits were well below last year.

3,801
Permits issued

Oct 1–29, all types

1,095
Construction permits

22% fewer than Oct 2025

107
Additions

Up from 76 a year ago

478
Postcard permits

Smaller jobs, up 33% on last year

The month at a glance

Permits issuedOct 1–29, 2026Sep 1–29, 2026Oct 1–29, 2025
All permits3,8013,9254,028
Construction1,0951,1411,408
Postcard478518360
Alteration and repair (construction)577637523
Additions10710576
New buildings293130
Solar7472466
Each column covers the 1st to the 29th of the month so the three are comparable. Additions are permits whose subtype or work description mentions an addition.

Two numbers stand out. Additions held at 107, level with September and 41% above last October, even as the overall count slipped. And solar permits fell from 466 in October 2025 to 74 this October, which accounts for much of the drop in construction permits year over year.

Postcard permits, the quicker route DC uses for smaller, simpler jobs, rose 33% on last year. More small jobs are going through the fast lane, while the larger construction permits that carry the most work are down.

Where the work is

Construction permits by ward, Oct 1–29
  • Ward 2266
  • Ward 6212
  • Ward 4131
  • Ward 5131
  • Ward 3116
  • Ward 185
  • Ward 785
  • Ward 869

Ward 2, which takes in downtown, Georgetown and Dupont Circle, led on construction permits, as it usually does with its mix of commercial and residential buildings. Ward 6, from Capitol Hill to the Navy Yard, was second. For residential additions, the order changes:

Additions by ward, Oct 1–29
  • Ward 624
  • Ward 220
  • Ward 418
  • Ward 316
  • Ward 110
  • Ward 510
  • Ward 86
  • Ward 73

Wards 6, 4 and 3 together had more than half of the city's additions. These are the rowhouse and single-family neighborhoods where owners add space rather than move: Capitol Hill, Petworth and Brightwood, and upper Northwest.

What kind of work

Permit subtypeIssued Oct 1–29
Electrical891
Plumbing and gas797
Alteration and repair516
Mechanical316
Building213
Plumbing195
Solar system74
Addition, alteration and repair61
Top subtypes. Trade permits (electrical, plumbing, mechanical) are often issued alongside or after a main building permit.

More than half of all permits were trade permits: electrical, plumbing and gas, and mechanical. Searching the work descriptions, 168 permits mentioned a roof and 95 mentioned a kitchen.

What it means for contractors

  • Additions are holding up. For remodelers and design-build firms, the steady flow of additions in Wards 6, 4 and 3 is the most useful signal in this report.
  • The jobs are getting smaller. More postcard permits and fewer full construction permits suggest owners are doing targeted work rather than whole-house projects.
  • Solar has slowed sharply. Installers and roofers who pair roof work with solar will see far fewer of those permits than a year ago.
  • Trade permits follow the main permit. An electrical or plumbing permit at an address with a recent alteration permit usually means the job is moving. For subcontractors, that's the moment to be in touch with the general contractor.

How we counted

  • Source: DC Department of Buildings permit records published on DC's open data portal: the "Building Permits – 2026" layer, and "Building Permits – 2025" for last year.
  • Dates: permits by issue date. On November 2, the latest issue date in DC's feed was October 29, so October 30 and 31 aren't included. We used the 1st to the 29th for every month in the table so the comparison is fair.
  • Additions: permits whose subtype or work description mentions an addition. A few may be counted in more than one row of the table.
  • No dollar values: DC's open permit data shows fees paid, not project value, so this report doesn't estimate job sizes.
  • Records can change: the Department of Buildings updates records after they're issued, so a later count may differ slightly.