In Montgomery County, residential building permits are issued by the Department of Permitting Services (DPS). Plumbing and gas permits come from WSSC Water, and several towns in the county have their own permit rules as well. Here's how it fits together.

What needs a permit

DPS says a permit is likely required for:

  • Additions: anything that extends the area, height or footprint of a house.
  • Alterations: reconstruction or renovation of an existing structure, other than a repair. Interior alterations count.
  • Decks: all decks, regardless of height above the ground.
  • Accessory structures such as garages and sheds, plus fences, retaining walls, pools and hot tubs.
  • Electrical work, and replacing heating or HVAC equipment.
  • Exterior work on a historic property.
  • Driveway aprons at the street, and land disturbance over 5,000 sq ft or 100 cubic yards of earth.

What usually doesn't

According to DPS, these usually don't need a building permit, though the work still has to meet code:

  • Roof covering only, siding and gutters.
  • Cabinets, floor coverings, and painting or repairing walls.
  • Driveways on your lot, patios and private walkways.
  • Windows and doors that don't change the size of the opening, and storm windows replaced in kind.
  • Replacing an electrical receptacle in the same location.
  • Retaining walls 48 inches or lower with no extra load above them.
  • Small prefabricated pools under 18 inches deep, retractable awnings and play equipment.

DPS's list doesn't cover town or homeowners' association rules. Your town or HOA may still require approval.

Fast Track for small jobs

DPS's Residential Fast Track issues a permit in one to two days in most cases. It's for:

  • Single-level decks.
  • Sheds and other non-habitable structures under 200 sq ft.
  • Finishing a basement or attic up to 400 sq ft (no basement kitchen and no structural attic work).
  • Kitchen and bath remodels up to 400 sq ft.
  • Non-load-bearing alterations up to 400 sq ft.
  • Minor fire repairs and accessibility ramps.

Properties on a private well or septic system aren't eligible for Fast Track.

The steps

  1. Apply online through DPS's Apply & ePay and upload plans through ePlans. For simple single-level decks, the county's standard deck details can stand in for drawings.
  2. Pay the filing fee. A non-refundable filing fee is due when you apply and the rest before the permit is released. Additions and alterations are priced per square foot, and decks, fences, retaining walls and pools have flat fees. DPS publishes the current fee schedule for estimates and sets the final amount.
  3. Post the sign (additions). For an addition, a yellow notice sign has to go up within 3 business days of DPS receiving the application and stay up for 30 days after the permit is issued.
  4. Plan review. Reviewers check the drawings against county and state codes. If they need changes, you get a notice and upload revised plans in ePlans.
  5. Inspections. Request them online at least 24 hours ahead with your permit number. Keep the permit and approved plans on site. A typical alteration goes footings, foundation, WSSC plumbing rough-in, framing and close-in, insulation, WSSC final, then the DPS final. DPS won't do close-in or final inspections until WSSC has approved the plumbing.

Who can apply

  • Homeowners can apply for their own permits only if they own the property, and DPS says some permit types aren't open to homeowners. An owner acting as builder signs a statement that they'll serve as the general contractor.
  • Contractors list their license number on the application, either a Maryland Home Improvement Commission (MHIC) license or a Montgomery County builder's license.
  • MHIC licensing matters to you as an owner. In Maryland, only MHIC-licensed contractors may contract with homeowners for home improvements, and the state's Guaranty Fund (up to $30,000) only covers work by licensed contractors. Look up a license before you hire. New home construction is registered separately, with the Attorney General's office.
  • Electrical permits need a valid parent building permit number.

Plumbing and gas: WSSC Water

Plumbing and gas permits are issued by WSSC Water, not DPS. WSSC says most plumbing projects must be done by a WSSC-licensed plumber or gasfitter. Homeowners can do some plumbing work themselves, but gas work always needs a licensed gasfitter. Applications go through WSSC's permit services.

Towns with their own rules

DPS notes that several municipalities require their own building permit in addition to the county permit. Depending on the town, you may need city approval before applying to the county, the county permit first, both, or only one of them. DPS lists 22 municipalities and special taxing districts, including Rockville, Gaithersburg, Takoma Park, Kensington, Chevy Chase Village and Poolesville, with contact details on its municipalities page. If you live in one of them, call the town first.

Historic sites and zoning

  • Historic Area Work Permits: if your property is on the county's Master Plan for Historic Preservation, substantial exterior changes or demolition need a Historic Area Work Permit (HAWP), reviewed by Montgomery Planning's historic preservation staff and the Historic Preservation Commission. Interior work and ordinary maintenance are exempt. A HAWP doesn't replace the building permit: the approval letter and stamped plans go in with your permit application. Some towns, such as Kensington, Takoma Park and Chevy Chase Village, may review first.
  • Zoning: the county's zoning code is Chapter 59. DPS gives official zone determinations, and you can look up a property's zone on the county's zoning map. Height, setbacks and lot coverage are where additions most often run into limits.

How to look up a permit

  • DPS's eSearch searches by address, permit number, contractor or date, and shows reviews and inspections.
  • dataMontgomery publishes the Residential Permit dataset: every residential building permit issued since 2000, updated daily, with work type, declared value and dates. Scope's monthly Montgomery report is built from it.