In Washington, DC, building permits are issued by the Department of Buildings (DOB), formerly part of DCRA. Most work beyond simple repairs and finishes needs a permit. The good news is that DC has several routes, from a permit issued online in minutes to full plan review for larger projects.

What needs a permit

According to DOB, you need a permit for new buildings, additions, interior alterations (including finishing a basement), porches and decks, fences, sheds over 50 sq ft, retaining walls over 4 ft, gas and HVAC equipment, new plumbing fixtures, EV chargers, demolition and razing, and pools.

What doesn't, outside historic districts

Unless your property is in a historic district, DOB lists work that doesn't need a building permit, including:

  • Painting (other than fire-retardant paint), papering, tiling, carpeting and other floor coverings.
  • Cabinets, countertops and similar finish work.
  • Brick pointing, caulking, and patching or plaster repair.
  • Window screens and storm windows.
  • In-kind replacement of roofing, siding, gutters, downspouts and fascia, private sidewalks, driveways and patios, and up to 160 sq ft of non-fire-rated drywall.
  • Repairing an existing fence with the same materials.
  • One garden shed of 50 sq ft or less and under 10 ft tall.
  • Retaining walls of 4 ft or less at one- and two-family homes, with minimal land disturbance.

"In-kind" means a like material that matches the existing feature's proportions, appearance, texture, design, detail and dimensions. If you're in a historic district, check before relying on any of these exemptions.

Four routes to a permit

RouteForHow it works
Instant PermitDefined small scopes at one- and two-family homes, such as replacing up to 15 windows in kind, rooftop solar up to 15 kW, and some interior demolition and repairsIssued online through DC's Citizen Access Portal. Property owners can get building Instant Permits themselves. These were formerly called postcard permits.
Homeowner's CenterOne- and two-family homes: small additions, one-level decks, fences, garages and sheds up to 500 sq ft, window and door replacement, non-structural roof work, drywall up to 500 sq ftDOB works with the homeowner and other agencies and aims to issue the permit within five business days.
Digital Walk-ThroughSmall projects with plansPlans are uploaded through ProjectDox for a review completed in one business day, per DOB.
Standard plan reviewLarger or complex projectsPlans are routed to zoning, structural, mechanical/electrical/plumbing, fire, green building and energy reviews. DOB's own target for filed projects is 30 business days.
Scopes and timelines are as published by DOB. Other agencies' reviews, such as historic preservation, can add time.

The steps

  1. Find out what you need. The DOB Permit Wizard lists the permits your project requires, estimates the total permit cost, and shows the reviews, documents and inspections to expect.
  2. Apply. Small scopes go through Instant Permits; larger projects are filed and you upload plans through ProjectDox.
  3. Review. DOB checks the application is complete, then routes plans to each review. If a reviewer needs changes, the application goes on hold until you respond.
  4. Pay and get the permit. Fees are paid before issue, and you name your contractor or say you'll act as your own.
  5. Inspections. Book them in DOB's Tertius system. You can use a DOB inspector at no extra cost or a DOB-certified third-party agency, which charges its own fees.
  6. Keep it active. A permit expires if no inspection is approved within 12 months of issue, or if work stops for a year.

How fees are set

DOB sets fees by construction value for alterations and repairs, by volume for new construction, and as flat amounts for many items such as fences, sheds and trade work. A 10% enhanced fee is added. When you file, you pay a deposit of half the assessed fee, up to $20,000. DOB says permit fees aren't refundable once the permit is issued. The Permit Wizard gives an estimate for your project.

Who can pull the permit

  • Owners of one- and two-family homes can get building Instant Permits and use the Homeowner's Center, or authorize an agent in writing.
  • Electrical, plumbing, gas and mechanical permits are issued only to licensed trade professionals.
  • Home improvement contractors must hold a DC Home Improvement Contractor license from the Department of Licensing and Consumer Protection (DLCP). It requires insurance, a $25,000 surety bond, a sample contract and tax compliance. Ask to see it before you hire.

Historic districts and zoning

If your home is in a historic district or is a landmark, exterior work is reviewed by the Historic Preservation Office at the Office of Planning. According to its published process:

  • Minor work is usually answered in 1 to 3 days.
  • Staff review of items such as front window and door changes, or rear additions under 500 sq ft, takes about 5 days.
  • Projects that go to the Historic Preservation Review Board, such as new buildings, front additions and porches, visible roof additions and demolition, typically take 30 to 60 days from filing.
  • Interior work, and work that doesn't need a building permit, isn't subject to preservation review. There's no separate fee for the review.

Every permit is also checked against DC's Zoning Regulations by DOB's Office of the Zoning Administrator. If a project doesn't meet the rules, for example on height, lot coverage or setbacks, the owner can ask the Board of Zoning Adjustment for a variance or special exception. That relief isn't automatic and takes a public process.

How to look up a permit

  • Scout searches by address, permit number or license number, and shows plan review progress and certificates of occupancy.
  • Open Data DC publishes building permits for the last 30 days and a dataset for each year, including trade and supplemental permits. Scope's monthly DC report is built from these records.